Modular Classroom for Haddenham Community Infant School
A new 71m² classroom, built on site and ready for the start of the new school year.
Haddenham Community Infant School
Client: Haddenham Community Infant School
Location: Haddenham, Buckinghamshire
Project Type: Single modular classroom
Floor Area: 71m²
Capacity: 32 pupils
Build Time: 11 weeks
Project Overview
A New Classroom, Ready for September
Haddenham Community Infant School needed additional classroom capacity to accommodate rising pupil numbers, with a tight deadline to have the new learning space ready for the start of the September term.
BGR Modular Classrooms designed and constructed a permanent 71m² timber-framed classroom on site, creating a bright, energy-efficient teaching environment for up to 32 pupils.
From the school's first enquiry to pupils sitting at their desks, the entire project was completed within the summer period, demonstrating how quickly a high-quality permanent classroom can be delivered when programme, design and construction are carefully managed.
From Enquiry to Classroom in 11 Weeks
11 June: School enquiry received
12 June: Site visit completed and quotation issued
15 June: Quotation accepted
17 June: Pre-start meeting
18 June: BGR mobilised on site
4 September: Classroom complete and pupils at their desks
Designed for Everyday School Life
The new classroom provides a spacious, naturally lit teaching environment designed for year-round use.
Alongside the main 71m² teaching space, the building includes an integrated kitchenette and staff preparation area, WC facilities and accessible level-threshold access with a compliant wheelchair ramp.
Project Summary
Key Features:
71m² Teaching Space
Designed to comfortably accommodate up to 32 pupils.Timber-Framed Construction
Timber frame with cedar cladding and 140mm Rockwool wall insulation.Energy Efficient
150mm PIR insulation to the roof and floor, designed to achieve the stated Building Regulations Part L U-values.Heating & Ventilation
Fujitsu ceiling cassette air-source heat pump with mechanical extract ventilation.Minimal Groundworks
Ground screw pile foundations avoided the need for a concrete base and reduced disruption to the school site.20-Year Structural Warranty
Providing the school with confidence in its long-term investment.
Built On Site. Built Around the School.
Unlike modular classrooms that are manufactured as fixed units elsewhere and transported to the school, BGR classrooms are constructed on site.
For Haddenham Community Infant School, this allowed the building programme to be carefully managed around the school environment while creating a permanent classroom tailored to the school's requirements.
BGR's on-site construction approach also gives schools greater freedom over the size, layout and height of their buildings, without many of the transport restrictions associated with off-site modular units.
The Outcome
A Permanent Classroom Built for the Future
In just 11 weeks from mobilisation, Haddenham Community Infant School gained a fully operational new classroom ready for pupils at the beginning of the September term.
The finished building provides additional capacity for 32 pupils in a comfortable, accessible and energy-efficient learning environment, while giving the school a permanent addition to its estate rather than a short-term classroom solution.